A continuity plan written three years ago has never been exercised. What is the most likely problem with it now?
Show the answer
Answer: C. Staff, systems and contacts in it have changed and it no longer matches reality
Plans decay quietly as the organisation changes. Exercising is what keeps the document connected to the real environment.
Source: NIST SP 800-34 Rev. 1 (NIST) — SP 800-34 Rev. 1 § 3.5 Plan Testing, Training, and Exercises