Which two elements must a change management process require before an authorised change is applied? Choose two.

  1. A signed non-disclosure agreement
  2. A CVSS score for the change
  3. A rollback plan
  4. A stated impact and an approval
Show the answer

Answer: C. A rollback plan
D. A stated impact and an approval

Change management exists to keep an authorised change from becoming an outage: impact, approval, rollback and a record.