How does continuity of operations planning differ from information system contingency planning?

  1. It applies only to physical facilities
  2. It is performed only after an incident
  3. It covers keeping the mission running, including people, facilities and suppliers
  4. It replaces the business impact analysis
Show the answer

Answer: C. It covers keeping the mission running, including people, facilities and suppliers

Restoring a system is narrower than keeping the organisation delivering, which may need staff, premises and vendors too.

Source: NIST SP 800-34 Rev. 1 (NIST) — SP 800-34 Rev. 1 § 2 Background