Which two activities belong to the prepare phase of executing a patch response? Choose two.
Show the answer
Answer: B. Scheduling the work through change management
D. Acquiring, validating and testing the patch
Preparation covers obtaining and testing the patch and coordinating deployment. Rescanning belongs to verification.
Source: NIST SP 800-40 Rev. 4 (NIST) — SP 800-40 Rev. 4 § 2.3 Risk Response Execution