A manager decides, during a finding review, how much risk the organisation is willing to accept. What is wrong with deciding it at that point?
Show the answer
Answer: C. Risk tolerance is set during framing, not case by case
Deciding tolerance per finding lets the answer follow the finding. Framing fixes it in advance so assessments are measured consistently.
Source: NIST SP 800-30 Rev. 1 (NIST) — SP 800-30 Rev. 1 § 2.3 Risk Framing